top of page

Prima Energy Announces Final Investment Decision for the Ande-Ande Lumut Oilfield in Indonesia

24 November 2026

PT Prima Petroleum Energy (‘Prima Energy’) announced today that it has taken the final
investment decision (‘FID’) for Phase One of the Ande-Ande Lumut (‘AAL’) oil development
in the Northwest Natuna PSC working area, located in the Natuna Sea offshore Indonesia.

AAL has certified resources of 56.4 million barrels of oil. Phase One capital investment is
estimated at $515 million, with first oil expected in 2028. Prima Energy Northwest Natuna
Pte Ltd (‘PENN’) is the operator of the Northwest Natuna PSC, with a 50% interest,
alongside Prima Energy AAL Singapore Pte Ltd (50%).

AAL Project Background
AAL is a heavy oil field in the offshore Northwest Natuna PSC, located in approximately 70m
of water in the Natuna Sea. Following the discovery well in 2000, the field was appraised
through 3D seismic acquisition and the drilling of three additional wells, supported by logging,
coring and testing to confirm reservoir size and productivity.

AAL is estimated to contain at least 300 million Stock Tank Barrels of Oil Initially In-Place
(‘STOIIP’). SKK Migas approved the Plan of Development Revision 1 (PoD Rev.1) in March
2024. Since then, the development concept has been further optimized through studies and
Front-End Engineering and Design (‘FEED’). A Well-head Central Processing Platform
(‘WHCPP’) EPCI contract has been tendered and negotiated; long-lead items have been
ordered; and drilling plans are well advanced.

AAL Project Description
Development of the AAL Field is planned in phases, with future phases to be informed by
the results and lessons learned from Phase One. Phase One comprises:

1) Installation of a six-pile WHCPP with 16 well slots (able to host 26 wells) and processing
capacity of 20,000 barrels of oil per day, 100,000 barrels of water per day and 110,000
barrels of liquid per day;

2) Charter of a spread-moored Floating Storage and Offloading (FSO) vessel providing
approximately 600,000 barrels of oil storage, utility support and offshore accommodation;
and

3) Drilling and completion of ten horizontal production wells optimised for heavy oil recovery.

The WHCPP EPCI contract is planned for execution in Q4 2026. Installation and hook-up of
the WHCPP and FSO are scheduled following the 2027/2028 monsoon season. Development
drilling is expected to commence in mid-2028, with first oil shortly thereafter and production
ramping up toward the facility design capacity of 20,000 barrels of oil per day. Future
development phases may include additional wells, increased processing capacity and
expanded production infrastructure, subject to separate technical, commercial and investment
approvals.

Market studies by CERA Consulting (S&P Global Energy) indicate strong Asia-Pacific demand
for heavy crude and significant refining capacity for crudes with characteristics similar to that
at AAL. The studies concluded that AAL crude is expected to achieve pricing broadly
comparable to Duri crude and may attract a premium to Dated Brent depending on refinery
configuration and product slate.

Pieters Utomo, CEO of Prima Energy, commented: ‘This is a very significant milestone for
Prima and for the Ande-Ande Lumut Field. We are excited about progressing this development
which will be an important growth driver for our E&P business in the coming years. With key
contracts about to be awarded, we look forward to working with our contractors on the project
to move it forward as quickly and efficiently as possible.’

Ends

For further information please contact:

Prima Energy
Peter Woodroof, Deputy CEO: peter.woodroof@primaenergy.id

Vigo Consulting
Patrick d’Ancona: patrick.dancona@vigoconsulting.com

bottom of page